As of now, CLNG has invested in a total of 36 vessels (including 11 Arc7 LNG vessels) with 30 of them already in operation. Serving as floating pipelines, these vessels will continue to provide safe and reliable maritime transportation services for our customers.
| Project | Vessel Name | Capacity | Yard | Delivery | Charterer |
|---|---|---|---|---|---|
| Dapeng Sun | 147,210 | Hudong-Zhonghua Shipyard | 2008-04-03 | Guangdong Dapeng LNG |
| Dapeng Moon | 2008-07-10 | ||||
| Dapeng Star | 2009-12-10 | ||||
| Fujian LNG Project | Min Rong | 2009-02-24 | CNOOC-Fujian LNG | ||
| Min Lu | 2009-08-13 | ||||
| Shanghai LNG Project | Shen Hai | 2012-09-20 | Shanghai LNG | ||
| PU Project | Pan Asia | 174,000 | Hudong-Zhonghua Shipyard | 2017-10-13 | Shell |
| Pan Americas | 2018-01-31 | ||||
| Pan Europe | 2018-07-10 | ||||
| Pan Africa | 2019-01-08 | ||||
| Yamal DSC Project | Boris Vilkitsky | 172,410 | DSME | 2017-12-26 | Yamal Trade |
| Fedor Litke | 2018-01-08 | ||||
| Georgiy Brusilov | 2018-12-10 | ||||
| Boris Davidov | 2019-01-18 | ||||
| Nikolay Zubov | 2019-02-22 | ||||
| Yamal TC Project | Eduard Toll | 2018-01-12 | |||
| Rudolph Samoylovich | 2018-09-06 | ||||
| Nikolay Yevgenov | 2019-06-03 | ||||
| Vladimir Voronin | 2019-08-13 | ||||
| Georgiy Ushakov | 2019-11-06 | ||||
| Yakov Gakkel | 2019-12-04 | ||||
| Shenzhen Gas Project |
Dapeng Princess | 79,916 | Hudong-Zhonghua Shipyard | 2023-02-16 | SINO-BENNY |
|
QE HZ Project | AL Tuwar | 174,176 | Hudong-Zhonghua Shipyard | 2025-5-16 | QatarEnergy |
| Al Mas'habiyyah | 2025-7-30 | ||||
| Fat'h Al Khair | 174,221 | 2025-8-25 | |||
| Mihzem | 174,281 | 2025-10-30 | |||
| Idd Al Shargi | 174,245 | 2025-12-10 | |||
| QE HHI Project | Al Zuwair | 172,961 | HHI | 2025-8-18 | QatarEnergy |
| Sharq | 2025-12-16 | ||||
| SHRA'OUH | 2026-1 -16 | ||||
| H3398 | 2026- - | ||||
| H3399 | 2026- - | ||||
| H3400 | 2026- - | ||||
| H3401 | 2026- - | ||||
| QE Ⅱ Project | H1912A | 270,926 | Hudong-Zhonghua Shipyard | 2028- - | QatarEnergy |
| H1916A | 2028- - |
LNGS MAIN PARTICULARS:
| Specifications |
Guangdong/Fujian/Shanghai Project |
PU Project |
Yamal Project (Arc7) |
|---|---|---|---|
| Length Overall |
292M | 290M | 299M |
| Breadth(Moulded) |
43.35M | 46.95M | 50M |
| Depth(Moulded at side at main deck) |
26.25M | 26.25M | 26.5M |
| Design Draught (Moulded) |
11.43M | 11.50M | 11.755M |
| Scantling Draught (Moulded) |
12.33M | 12.50M | 13.00M |
| Cargo Tank Type x Quantity |
GTT No.96 x 4 Tanks | GTT NO.96 x 4 Tanks | GTT NO.96-GW x 4 Tanks |
| Deadweight |
68,938 T | 80,480 T | 79,880 T |
| Cargo Tanks |
147,236 M3 | 174,000 M3 | 172,410 M3 |
| Main Steam Turbine MCR x RPM |
27,300 KW x 83 RPM | 23,400 KW x 69.1 RPM | 39,600 KW x 108 RPM |
| Propulsion |
Duel fuel steam engine propulsion | TFDE electric propulsion | DFDE+Azipod electric propulsion |
| Design Service Speed |
19.5 Kn with 27% Sea Margin | 19.5 Kn with 20% Sea Margin | 19.5 Kn with 21% Sea Margin |
| Boil-off Gas Rate |
≤0.150%/Day | ≤0.145%/Day | ≤0.130%/Day |
| Specifications |
Shenzhen Gas Project | QE HZ Project | QE HHI Project |
|---|---|---|---|
| Length Overall |
239M | 299M | 299M |
| Breadth(Moulded) |
36.6M | 46.40M | 46.40M |
| Depth(Moulded at side at main deck) |
21.0M | 26.25M | 26.5M |
| Design Draught (Moulded) |
8.50M | 11.50M | 11.50M |
| Scantling Draught (Moulded) |
9.50M | 12.50M | 12.50M |
| Cargo Tank Type x Quantity |
GTT NO.96-L03+ x 4 Tanks |
GTT NO.96-L03+ x 4 Tanks |
GTT Mark III Flex x 4 Tanks |
| Deadweight |
37,200 T | 80,280 T | 80,939 T |
| Cargo Tanks |
79,916 M3 | 174,000 M3 | 174,000 M3 |
|
Main Steam Turbine MCR x RPM
|
13,400 KW x 115.4 RPM | 24,680 KW x 75.0 RPM | 24,100 KW x 74.7 RPM |
| Propulsion |
Duel fuel diesel engine propulsion | Duel fuel diesel engine propulsion | Duel fuel diesel engine propulsion |
| Design Service Speed |
17.5 Kn with 15% Sea Margin | 19.5 Kn with 21% Sea Margin | 19.5 Kn with 21% Sea Margin |
| Boil-off Gas Rate |
≤0.140%/Day | ≤0.098%/Day | ≤0.085%/Day |